Import and export the construction schedule to MS Project
In brief: you can exchange your construction schedule with MS Project — via XML. BauMaster exports the schedule only as XML, which you open in MS Project; the other way round, users with an Expert licence import schedules created in MS Project (MPP or MS-Project-compatible XML) into BauMaster. Some BauMaster-specific information is lost in the exchange.
Prerequisites: import and export are reserved for the Expert licence; an admin is not needed for it. Import into BauMaster is only available in the desktop application (in the browser). The construction schedule does not exist on mobile. BauMaster exports no MPP files, only XML. You can import MPP files or MS-Project-compatible XML files.
Working MS-Project-compliant
If you work “MS-Project-compliant” in BauMaster — that is, avoiding everything MS Project does not support — you can exchange the construction schedule between the systems with little loss. Keep the construction schedule in BauMaster always up to date, since it is available to all project participants — including Viewers and Teamworkers — for reading and download.
Compatibility at a glance
This is how the functions behave when exchanging between BauMaster and MS Project:
| Function | BauMaster → MS Project | MS Project → BauMaster |
|---|---|---|
| Work items under work items | ❌ Converted into phases in MS Project and lose work-item-specific information | ❌ Does not exist in MS Project |
| Construction phases under construction phases | ✅ | ✅ |
| Tasks & entries in the construction schedule | ❌ Imported work items lose their references to BauMaster tasks & record entries | ❌ Lost references cannot be restored afterwards |
| Milestones | ✅ | ✅ |
| Status of work items & phases | ❌ The open/done logic does not exist in MS Project | ❌ Percentage sliders and completion dates do not exist in BauMaster |
| Non-working days & weekly working days (a 4-day week, for example) | ✅ | ✅ |
| Target/actual comparison | ❌ Not compatible | ❌ Not compatible |
| Additional information (trade) | ❌ Not compatible | ❌ Not compatible |
| Dependencies (work items) | ✅ | ✅ |
Export the construction schedule from BauMaster
Via the import/export button (icon at the top right) in the construction schedule you export the schedule as XML. Note that not all BauMaster functions can be carried over to MS Project (see the compatibility table above).
Import XML into MS Project (Windows)
- In MS Project, click “Open” in the menu.
- Next to “file name”, select the XML format.
- Decide how to import (as a new project or into an existing project) and click “Finish”.
- If conflicts occur, resolve them with the standard planning wizard.
Import MS Project into BauMaster
Users with an Expert licence can import schedules from MS Project — as an MPP file or as an MS-Project-compatible XML file. The import/export button appears at the top right (along with a button to delete the entire construction schedule).
- If entries already exist in the construction schedule, the imported MS Project plan is inserted below them.
- With very specific MS Project settings the interface may be incompatible.
Import is only available in the desktop application (in the browser).
FAQ
Does BauMaster export MPP files?
No. BauMaster exports XML only. For import, BauMaster accepts MPP files and MS-Project-compatible XML files (with an Expert licence).
Which information is lost in the exchange?
Among others: work items under work items, references to tasks/entries, the open/done status, the target/actual comparison and trades (see the compatibility table).
Who may import and export?
Users with an Expert licence; an admin is not needed. Import into BauMaster is only possible in the desktop application (in the browser).
Keywords: construction schedule MS Project