Help › Best Practices › Construction Documentation

Working with continuous records

In the construction process there are regular meetings between the parties at various stages — planning or client meetings, and above all the (weekly) site meeting on site.

For these recurring meetings it is best to keep the record as a continuous record. That gives you documentation without gaps, in which open tasks are carried forward automatically.

Unfinished tasks are carried over into the next record in a continuous record until their status is set to “done”. That keeps all open points in view.

Do not use a standard record for this requirement. How types with and without status behave is described in Record types in continuous records.

Create a continuous record

In the projects menu go to record styles and create a record style with the layout “continuous”, see Create, edit and delete record styles. In the records menu you then recognise in the record styles column from the label whether a record style is continuous.

How a continuous record works

The current continuous record (a site meeting record, for example) must always be closed — only then can you create the next continuous record. You close it when sending (checkbox “close record” next to the send button on the last page) or via the three-dot menu on the right of the record. All details on closing are in Records: overview, creating, copying and deleting. All entries still on “open” or “to review” are carried over into the next record.

Difference between the “standard” and “continuous” record types:

  1. With standard records, entries always stay in that one record. You can create any number of independent single records of a record style.
  2. With continuous records there is always only one active record being edited. The previous ones must be closed. Info points and completed points are not carried over; entries on “open”, “to review” and “continuous information” move into the next record.

Entries in closed records are “frozen”. What is still possible afterwards (status, “to be done by”, responsible person, new sub-entries) is described in the section “edit and close a record” in Records: overview, creating, copying and deleting. For continuous records this also applies to carried-over entries: new information — when, how and by whom a defect was fixed — you add via sub-entries.

Notes

Comments always relate to a specific entry. If an entry is carried over into the next record, its comments move with it automatically.

Points that apply generally to the current project are best captured in the opening text of the PDF record.

Continuous does not mean that an entry can be continued or changed in content in the next record. An open entry is passed into the new record, but its status can only be changed from “open” to “done”, for example (traffic light). If it stays “open”, it is carried over into the following record again.

Sub-entries also can no longer be changed once the record has been closed and the next record created. You can, however, add new sub-entries.

Editing carried-over entries

  • Carried-over entries can only be edited to a limited extent: responsible person, to be done from, to be done by and status.
  • You can still add comments.
  • New sub-entries are marked with a warning so it is clear they were added later. They do not appear in older versions of the record.

Important: if you change the status, “to be done from” or “to be done by” of a carried-over entry, the value changes in all previous records containing that entry too.

Opening text in the PDF record layout

You can enter the opening text (the generally applicable points) in the PDF record layout and save it as a template. That way it remains for the whole project duration. When sending, the opening text is printed at the top of the record and the closing text after the last entry. You can adjust both before every send or save them as a template. Ready-made text blocks are in Text templates for PDF records.

Comparison: standard and continuous records

Behaviour Standard record Continuous record
Records of the same style Several open or closed at the same time One record open — all earlier ones closed
Dependency Records independent of each other Records dependent on each other
Entry Always shown in only one record Unfinished entries appear in several records
Status (open, to review, done) No effect on the new record Affects the new record
Editing after closing No editing of entries possible No editing possible (carried-over entries too)

FAQ

When should I use a continuous record instead of a standard record?

Whenever open tasks should be tracked across several meetings — recurring site meetings, for example. Open entries are carried over into the next record automatically.

Can I still change carried-over entries in the next record?

No, carried-over entries stay frozen too. You add new information via sub-entries. What is generally still possible after closing is described in the record overview under “edit and close a record”.

Are comments carried over into the next record?

Yes. If an entry is carried over into the next record, its comments move with it automatically.